Please see the below programme for the Surface Dressing prep works starting Friday 17/04/2020. per attached TRO TTRO notice of intent – PH .
Please note that ‘A’ Roads will be carried out under night closures between the hours of 19:00 – 06:00. All other closures will be carried out on day works with no restrictions.
Task Name Duration Start
Tirley Lane 4 days Fri 17/04/20
Waste Lane 3 days Tue 21/04/20
A54 Chester Rd 2 nights Mon 27/04/20
A54 Oakmere Rd 2 nights Wed 29/04/20